01 October 2012

Waitrose Fit-out, Cowbridge



Project summary
 

  • Region: Cardiff
  • Value: £1,340,000
  • Contract terms: JCT Design & Build 2005
  • Contract length: 6 weeks
  • Procurement: Design + Build
  • Completed: October 2012
  • Site features and challenges: Short programme, management of deliveries via congested town centre, interface with main contractor whilst they completed external works
  • BREEAM: Very Good
  • Community: Renovation of nature area at local Y Bont Faen primary school
  • Customer Satisfaction: 88%
     

This project consisted of the retail fit-out to a new developer's store shell, just off Cowbridge High Street. Works comprised the installation of an M+E plant and associated features, including refrigeration and ducting apparatus, the laying of terrazzo flooring, ceiling fitting and associated electrical components, goods shelves, and meat, fish and delicatessen counters. GIA = 28,000 ft²